Conversion of (e) unconditioned storage space into (n) 775sf adu with 1 bed & 1 bath,storage room, trash toter enclosure & 1hr hallway connecting the adu to building foyer. (n)wood framed steps on (e) sloped concrete floor.replace rear yard deck with new.

Timeline
Key dates from the city record.
Filed
Feb 27, 2025
Issued
Feb 3, 2026 (11 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 6 departments
Comments issued
8 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 22, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Feb 24, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Mar 3, 2025Administrative

Zoning review

Planning · CP-ZOC

Mar 5, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 13, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 12, 2025Not Applicable

Mechanical and energy plan review

Building Inspection · MECH

Mar 13, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 10, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 6, 2025Approved

Urban forestry

Public Works · DPW-BUF

Mar 18, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 5, 2025Approved

Permit Processing Center

Building Inspection · PPC

Sep 18, 2025Administrative

Fire prevention review

Fire Department · SFFD

May 1, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

May 6, 2025Approved

Building plan review

Building Inspection · BLDG

May 9, 2025Issued Comments

Zoning review

Planning · CP-ZOC

May 22, 2025Approved

Urban forestry

Public Works · DPW-BUF

Jul 17, 2025Approved

Fire prevention review

Fire Department · SFFD

Jun 23, 2025Approved

Zoning review

Planning · CP-ZOC

Jun 23, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 26, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 27, 2025Approved

Fire prevention review

Fire Department · SFFD

Jul 18, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 24, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 18, 2025Approved

Zoning review

Planning · CP-ZOC

Aug 19, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 19, 2025Approved

Fire prevention review

Fire Department · SFFD

Aug 20, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Aug 21, 2025Approved

Urban forestry

Public Works · DPW-BUF

Aug 29, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 26, 2025Approved

Development fee collection

Building Inspection · DFCU

Sep 2, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Feb 3, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$231,010
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mahya Salehi Fadardi

Mahya Salehi Fadardi

ArchitectC-38610
Siavash Soroushian

Eas Designers

EngineerC94523
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202501138193 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record