1040 Bryant St
San Francisco permit 202501148280 · South of Market
Change of use from b/u to b/f-1 continuation of existing industrial (cultivational) ag. for cannabis and new distribution (wholesale sales)
- Filed
- Feb 10, 2025
- Issued
- Nov 12, 2025 (9 months after filing)
- Completed
- Dec 16, 2025 (1 month after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 28 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 14, 2025 | Jan 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 14, 2025 | Jan 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 14, 2025 | Jan 14, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2025 | Jan 14, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 14, 2025 | Jan 14, 2025 | Administrative |
Public health review Public Health · HEALTH | Jan 16, 2025 | Jan 16, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jan 25, 2025 | Feb 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2025 | Feb 11, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 11, 2025 | Mar 3, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 11, 2025 | Mar 7, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 11, 2025 | Oct 29, 2025 | Administrative |
Building plan review Building Inspection · BLDG | May 5, 2025 | Jul 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 17, 2025 | Jun 23, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 24, 2025 | Jun 24, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 26, 2025 | Jun 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 12, 2025 | Aug 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 29, 2025 | Aug 29, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 24, 2025 | Sep 30, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Sep 24, 2025 | Sep 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2025 | Sep 25, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 30, 2025 | Sep 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 30, 2025 | Sep 30, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 24, 2025 | Oct 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 24, 2025 | Oct 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2025 | Oct 28, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 24, 2025 | Oct 24, 2025 | Approved |
Public Health HEALTH-HM | Oct 24, 2025 | Oct 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 29, 2025 | Nov 12, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,507
| Name | Role | License on permit |
|---|---|---|
| Peter Petruzzi Linea 3 | Architect | C-18480 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2016