3220 Sacramento St
San Francisco permit 202501158356 · Presidio Heights
Interior renovation to convert (e) u-lab classroom to offices and student lounge. replacement of hvac unit w/ new erv,heat pumpunits, diffusers and grills.
- Filed
- Apr 3, 2025
- Issued
- Jun 11, 2025 (2 months after filing)
- Completed
- Sep 9, 2025 (3 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 15, 2025 | Jan 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 15, 2025 | Jan 15, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Jan 15, 2025 | Jan 15, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 15, 2025 | Jan 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 15, 2025 | Jan 15, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 14, 2025 | Mar 28, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 18, 2025 | Apr 3, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 3, 2025 | May 8, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 3, 2025 | Jun 3, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 3, 2025 | May 13, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 3, 2025 | Apr 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 3, 2025 | Apr 29, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 3, 2025 | Jun 6, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 23, 2025 | Apr 23, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 28, 2025 | Apr 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 29, 2025 | May 30, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | May 29, 2025 | May 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 29, 2025 | Jun 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 6, 2025 | Jun 11, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| J Aaron Thornton | Architect | C-35066 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2024