1150 Castro St
San Francisco permit 202501168525 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa 202310108364 reconstruction due to fire damage.at upper unit, revision to non-structural interior partition layout. replace in-kind (e) forced air system at both levels.
- Filed
- Jan 16, 2025
- Issued
- May 22, 2025 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 6 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Jan 16, 2025 | Jan 16, 2025 | Approved |
Intake Building Inspection · INTAKE | Jan 16, 2025 | Jan 16, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Feb 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2025 | Feb 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 14, 2025 | Feb 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 22, 2025 | May 22, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Jennifer Ann Butler | Authorized agent-others | C38101 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2020