244 16th Av
San Francisco permit 202501178530 · Outer Richmond
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to permit# 202009305567.reduce scope & cost of work.renovation and rear expansion the size of approved expansion on the 1/f is reduced.approved expansion on 2/f & attic/top level is eliminated existing attic level to remain/has a 7'-0" ceiling and therefore non-habitable. no f/s installed.
- Filed
- Jan 17, 2025
- Issued
- May 16, 2025 (4 months after filing)
- Completed
- Oct 14, 2026 (17 months after issuance)
- Review stops
- 19 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 15, 2025 | Jan 28, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2025 | Jan 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 28, 2025 | Feb 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 28, 2025 | Feb 26, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 28, 2025 | Feb 26, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 28, 2025 | Jan 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2025 | Feb 3, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 28, 2025 | Apr 17, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 21, 2025 | Mar 27, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 21, 2025 | Mar 27, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 21, 2025 | Apr 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 21, 2025 | Mar 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 21, 2025 | Mar 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 28, 2025 | Apr 1, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 28, 2025 | Apr 1, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 28, 2025 | Apr 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 28, 2025 | Apr 4, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 31, 2025 | Mar 31, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 17, 2025 | May 16, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Maria Clara Sanchez Quiroz | Architect | C-35031 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022