1317 Haight St
San Francisco permit 202501178571 · Haight Ashbury
Prop h: commericail ti - new cafe/limited restaurant at (e) vacant space (change of use). new finishes & equipment. no structural work. new mech/plumbing & electrical under separate permit.
- Filed
- Jan 17, 2025
- Issued
- Mar 7, 2025 (2 months after filing)
- Completed
- Sep 12, 2025 (6 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 19 stops across 6 departments
- Comments issued
- Twice, by Building Inspection, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 17, 2025 | Jan 23, 2025 | Administrative |
Code enforcement Building Inspection · CES | Jan 22, 2025 | Jan 22, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 23, 2025 | Feb 12, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 24, 2025 | Jan 24, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 24, 2025 | Jan 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2025 | Jan 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 27, 2025 | Jan 31, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 27, 2025 | Jan 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 27, 2025 | Jan 27, 2025 | Approved |
Public health review Public Health · HEALTH | Jan 28, 2025 | Jan 28, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Feb 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 5, 2025 | Feb 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 5, 2025 | Feb 7, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 5, 2025 | Feb 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 6, 2025 | Feb 6, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 6, 2025 | Feb 6, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 7, 2025 | Feb 7, 2025 | Approved |
Public health review Public Health · HEALTH | Feb 12, 2025 | Feb 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 12, 2025 | Mar 7, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $50,500
| Name | Role | License on permit |
|---|---|---|
| Michael Steiner Steiner Architecture | Architect | C-31950 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2015