901 Market St
San Francisco permit 202501218737 · South of Market
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to architecutral, plumbing, electrical and mechanical tenant improvement. ref t.i permit 202211186816.
- Filed
- Jan 21, 2025
- Issued
- Mar 20, 2025 (2 months after filing)
- Completed
- Not completed yet
- Review stops
- 19 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 21, 2025 | Jan 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 21, 2025 | Jan 21, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2025 | Jan 21, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 21, 2025 | Jan 21, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Feb 5, 2025 | Feb 5, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 5, 2025 | Feb 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Mar 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2025 | Feb 5, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 5, 2025 | Feb 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 5, 2025 | Feb 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 5, 2025 | Feb 5, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 12, 2025 | Feb 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2025 | Feb 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2025 | Mar 11, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 11, 2025 | Mar 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 11, 2025 | Mar 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2025 | Mar 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 20, 2025 | Mar 20, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 20, 2025 | Mar 20, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Page Winkler Mcg Architecture | Architect | C31839 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023