Scope of work
As written on the permit application.

Renovation for imaging department on a portion of the 1st fl. work includes ti with interior non structural partitions, ceilings, casework, equipment & mep. selective demo under a separate permit.

Timeline
Key dates from the city record.
Filed
Mar 10, 2025
Issued
Jul 25, 2025 (5 months after filing)
Completed
Apr 15, 2026 (9 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 6 departments
Comments issued
7 times, by Building Inspection, Fire Department
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Jan 22, 2025Administrative

Zoning review

Planning · CP-ZOC

Jan 22, 2025Not Applicable

Building plan review

Building Inspection · BLDG

Jan 22, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Jan 22, 2025Issued Comments

Public health review

Public Health · HEALTH

Jan 27, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 28, 2025Approved

Fire prevention review

Fire Department · SFFD

Jan 29, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Mar 4, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Mar 10, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Apr 18, 2025Issued Comments

Electrical plan review

Building Inspection · MECH-E

Mar 19, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

May 8, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Jul 16, 2025Administrative

Structural plan approval

Building Inspection · PAD-STR

Apr 15, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 6, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

May 9, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 7, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Jul 3, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 14, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Jul 10, 2025Approved

Fire prevention review

Fire Department · SFFD

Jul 8, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 14, 2025Approved

Public health review

Public Health · HEALTH

Jul 9, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 25, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$7,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Sujendra Kavin Mishra

Boulder Associates

ArchitectC32978
Emily Guglielmo

Martin / Martin, Inc.

EngineerS5902
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202501228783 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record