Renovation for imaging department on a portion of the 1st fl. work includes ti with interior non structural partitions, ceilings, casework, equipment & mep. selective demo under a separate permit.
- Filed
- Mar 10, 2025
- Issued
- Jul 25, 2025 (5 months after filing)
- Completed
- Apr 15, 2026 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 24 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 22, 2025 | Jan 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 22, 2025 | Jan 22, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Jan 22, 2025 | Jan 22, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 22, 2025 | Jan 22, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Jan 27, 2025 | Jan 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2025 | Jan 28, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 29, 2025 | Jan 29, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 14, 2025 | Mar 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 10, 2025 | Mar 10, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Mar 10, 2025 | Apr 18, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 10, 2025 | Mar 19, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 10, 2025 | May 8, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 10, 2025 | Jul 16, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Mar 12, 2025 | Apr 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 1, 2025 | May 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 6, 2025 | May 9, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 3, 2025 | Jul 7, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 3, 2025 | Jul 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 8, 2025 | Jul 14, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 8, 2025 | Jul 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 8, 2025 | Jul 8, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 8, 2025 | Jul 14, 2025 | Approved |
Public health review Public Health · HEALTH | Jul 9, 2025 | Jul 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 16, 2025 | Jul 25, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $7,000,000
| Name | Role | License on permit |
|---|---|---|
| Sujendra Kavin Mishra Boulder Associates | Architect | C32978 |
| Emily Guglielmo Martin / Martin, Inc. | Engineer | S5902 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025