655 Kansas St
San Francisco permit 202501228846 · Potrero Hill
Unit 501-replace (e) deck that was removed in 2022 10x 15 ft (150 sf)
- Filed
- Jan 22, 2025
- Issued
- Feb 12, 2025 (within 1 month of filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 6 stops across 2 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Jan 22, 2025 | Jan 22, 2025 | Approved |
Intake Building Inspection · INTAKE | Jan 22, 2025 | Jan 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 22, 2025 | Jan 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 22, 2025 | Jan 22, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 12, 2025 | Feb 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 12, 2025 | Feb 12, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $5,000
| Name | Role | License on permit |
|---|---|---|
| Michael Bernard Harris Michael Harris Architecture | Architect | C-15349 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2015