7 07th Av
San Francisco permit 202501249018 · Inner Richmond
Lower garage floor. new retaining walls sistered to existing walls. widen garage door. adjust driveway scope. no work at upper levels.
- Filed
- Feb 13, 2025
- Issued
- Oct 22, 2025 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 28 stops across 4 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 24, 2025 | Jan 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 24, 2025 | Jan 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 24, 2025 | Jan 24, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jan 30, 2025 | Feb 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 4, 2025 | Feb 13, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 13, 2025 | Feb 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 13, 2025 | Mar 11, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 13, 2025 | Apr 4, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2025 | Feb 20, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 13, 2025 | Oct 15, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 17, 2025 | Apr 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 24, 2025 | Apr 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2025 | Apr 24, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2025 | Apr 29, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2025 | May 2, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 17, 2025 | Aug 18, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 16, 2025 | Jul 22, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 6, 2025 | Aug 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 8, 2025 | Aug 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 8, 2025 | Sep 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2025 | Aug 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 8, 2025 | Aug 18, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 8, 2025 | Sep 9, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2025 | Sep 17, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2025 | Sep 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2025 | Sep 10, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 8, 2025 | Sep 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 15, 2025 | Oct 22, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $165,000
| Name | Role | License on permit |
|---|---|---|
| Gisela Schmoll Gisela Schmoll Architect Pc | Architect | C33615 |
| Victor Ramos Ashley & Vance Engineering | Engineer | C86568 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2015