328 A Mount Vernon Av

San Francisco permit 202501249034 · Outer Mission

ADUFull plan reviewComplete
Street view · Apr 2022
Google Street View of 328 A Mount Vernon Av, Apr 2022
Scope of work
As written on the permit application.

Ab1114:construction of a 400-square-foot one bed adu on ground/basement level of(e)sfd w/ full bath, kitchen & dining area w/ access to the rear yard.it will be equipped with(n) electric appliances, water heater & mini split heat pump system.surface renovations to the main level kitchen & bath.

Timeline
Key dates from the city record.
Filed
Feb 25, 2025
Issued
Jul 8, 2025 (4 months after filing)
Completed
Sep 16, 2026 (14 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 6 departments
Comments issued
9 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Utilities, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 31, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Feb 21, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Feb 26, 2025Administrative

Zoning review

Planning · CP-ZOC

Mar 11, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 10, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 10, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 28, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 27, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 4, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Jul 2, 2025Administrative

Zoning review

Planning · CP-ZOC

Apr 14, 2025Approved

Building plan review

Building Inspection · BLDG

Apr 11, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 22, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 11, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Apr 14, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Apr 18, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 14, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

May 29, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

May 30, 2025Approved

Development fee collection

Building Inspection · DFCU

May 30, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Jul 8, 2025Administrative

Urban forestry

Public Works · DPW-BUF

Jul 1, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Jul 2, 2025Approved

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$388,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Sujin Sung

Sujin Sung Engineering

EngineerC78186
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202501249034 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record