1875 Geneva Av
San Francisco permit 202501249048 · Visitacion Valley
Remove 650 sf of unpermitted construction,remove 281 sf unpermitted patio, add a new hallway to access the new adu,add a new 500 sf attached adu with one toilet and two bedrooms
- Filed
- Mar 10, 2025
- Issued
- Jul 24, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 24 stops across 6 departments
- Comments issued
- 7 times, by Permit Center, Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 16, 2025 | Jan 31, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 12, 2025 | Feb 26, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 5, 2025 | Mar 11, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 11, 2025 | Apr 3, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 11, 2025 | Mar 18, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2025 | Apr 13, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 11, 2025 | Mar 13, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 11, 2025 | Mar 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2025 | Mar 17, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 11, 2025 | In progress | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Mar 19, 2025 | Mar 19, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 13, 2025 | May 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 15, 2025 | May 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 15, 2025 | May 30, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2025 | May 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 12, 2025 | Jun 12, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 13, 2025 | Jun 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 13, 2025 | Jun 13, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 13, 2025 | Jun 13, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 13, 2025 | Jun 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 13, 2025 | Jun 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 13, 2025 | Jun 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 18, 2025 | Jul 24, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 24, 2025 | Jul 24, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $208,974
| Name | Role | License on permit |
|---|---|---|
| Lei Zheng | Architect | C69809 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2023