17 Jordan Av
San Francisco permit 202501309370 · Presidio Heights
Connvert non-habitable to habitable, inter remodel all areas incl kitchen, bathrooms and living areas, demo 1-bath, add 3-baths, add 1-bedroom at 1/f. replace (e)foundation, raise house approx 18". local seismic strengthening. new dormers @ roof. new heat system. enclose 1/f area under (e)addition..
- Filed
- Mar 3, 2025
- Issued
- Jun 20, 2025 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 6 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 28, 2025 | Feb 11, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 11, 2025 | Feb 26, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2025 | Mar 3, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 3, 2025 | May 20, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 3, 2025 | Apr 4, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 3, 2025 | Apr 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2025 | Apr 6, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 3, 2025 | Mar 4, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2025 | Mar 4, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2025 | Mar 10, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 3, 2025 | Jun 12, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Mar 21, 2025 | Mar 21, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2025 | Mar 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2025 | Apr 29, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 1, 2025 | May 5, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2025 | May 20, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 21, 2025 | May 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 22, 2025 | May 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 27, 2025 | May 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 3, 2025 | Jun 3, 2025 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Jun 6, 2025 | Jun 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2025 | Jun 20, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Benjamin Ian Farrell Farrrell Architecture | Architect | C29919 |
| Dustin Muhn Parker Framework Engineering | Engineer | 82063 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2015