88 06th St
San Francisco permit 202502039519 · South of Market
Replace existing cooling system wit new split system. replace existing fluid cooler with new, same size capacity
- Filed
- Feb 3, 2025
- Issued
- Aug 25, 2025 (7 months after filing)
- Completed
- Aug 26, 2026 (12 months after issuance)
- Review stops
- 12 stops across 4 departments
- Comments issued
- Once, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Feb 3, 2025 | Feb 3, 2025 | Administrative |
Intake Building Inspection · INTAKE | Feb 3, 2025 | Feb 3, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 3, 2025 | Feb 3, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 3, 2025 | Feb 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 3, 2025 | Feb 3, 2025 | Approved |
Public health review Public Health · HEALTH | Feb 3, 2025 | Feb 3, 2025 | Not Applicable |
Intake Building Inspection · INTAKE | Aug 25, 2025 | Aug 25, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 25, 2025 | Aug 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 25, 2025 | Aug 25, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 25, 2025 | Aug 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 25, 2025 | Aug 25, 2025 | — |
Central Permit Bureau Building Inspection · CPB | Aug 25, 2025 | Aug 25, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $89,000
| Name | Role | License on permit |
|---|---|---|
| Joe Terhemen Igber Sedr Consulting | Engineer | C78132 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025