380 Valencia St
San Francisco permit 202502049646 · Mission
Change of occupancy type e to i-4. update restrooms to ada compliance, remove partitions, move sinks,
- Filed
- Feb 18, 2025
- Issued
- Jun 18, 2025 (4 months after filing)
- Completed
- Jul 29, 2025 (1 month after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 18 stops across 7 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 1, 2025 | Feb 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 18, 2025 | Feb 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 19, 2025 | Feb 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 19, 2025 | Mar 4, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 19, 2025 | Apr 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 19, 2025 | Mar 14, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 19, 2025 | Feb 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 19, 2025 | Feb 27, 2025 | Administrative |
Public health review Public Health · HEALTH | Feb 19, 2025 | Feb 20, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Feb 19, 2025 | Apr 14, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 19, 2025 | Mar 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 19, 2025 | Apr 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 19, 2025 | Mar 21, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2025 | Mar 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 28, 2025 | Apr 1, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 28, 2025 | Apr 7, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 28, 2025 | Apr 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 14, 2025 | Jun 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $15,000
| Name | Role | License on permit |
|---|---|---|
| Lawrence Edward Schadt Gelfand Partners Architects | Architect | C29266 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026