San Francisco permit 202502059722 · North Beach

ADUFull plan reviewFiled
Street view · Mar 2022
Google Street View of 433 Lombard St #0, Mar 2022
Scope of work
As written on the permit application.

Legalization of unauthorized unit (unit 8- 433a lombard) as state adu. referance work proposed under seperate permit, which is to legalize unit 7 under the legalization program.

Timeline
Key dates from the city record.
Filed
Nov 5, 2025
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 6 departments
Comments issued
10 times, by Permit Center, Building Inspection, Fire Department, Public Works, Public Utilities
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 18, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Sep 29, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Nov 5, 2025Administrative

Zoning review

Planning · CP-ZOC

Nov 25, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 20, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 14, 2025Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Nov 6, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 17, 2025Approved

Urban forestry

Public Works · DPW-BUF

Dec 3, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Nov 14, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

In progress—

Mechanical plan review quality control

Building Inspection · MECH-QC

Nov 19, 2025Approved

Zoning review

Planning · CP-ZOC

Jun 11, 2026Approved

Building plan review

Building Inspection · BLDG

Jun 17, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 11, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Jun 12, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jun 8, 2026Approved

Urban forestry

Public Works · DPW-BUF

Jul 2, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 23, 2026Issued Comments

Building plan review

Building Inspection · BLDG

In progress—

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Fire Department housing review

Fire Department · SFFD-HQ

In progress—

Public Utilities Commission review

Public Utilities · SFPUC

In progress—

Development fee collection

Building Inspection · DFCU

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Filed
Estimated cost
$5,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Steven Carl Geiszler

Geiszler Architects

ArchitectC24557
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202502059722 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record