63 Walter St
San Francisco permit 202502079899 · Castro/Upper Market
Legalize (e) 3/f roof deck in rear yard within buildable area. new guardrail. legalize (e) steps to roof deck.
- Filed
- Feb 7, 2025
- Issued
- Jul 17, 2025 (5 months after filing)
- Completed
- Jun 15, 2026 (11 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 7 stops across 3 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Feb 7, 2025 | Feb 7, 2025 | Administrative |
Intake Building Inspection · INTAKE | Feb 7, 2025 | Feb 7, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 7, 2025 | Feb 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 10, 2025 | Feb 10, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 21, 2025 | Feb 21, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 21, 2025 | Feb 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 17, 2025 | Jul 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $30,000
| Name | Role | License on permit |
|---|---|---|
| Aaron Michael Lim Aaron Lim Design | Architect | C37034 |
| Erik Mcgregor Wmstructural | Engineer | S6802 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2015