388 Market St
San Francisco permit 202502100005 · Financial District/South Beach
14/f-ste 1460: demolition of (e) flr finishes and (e) partitions and (e) ceiling. the new proposed design includes: offices, break area, open office area, one conference room and new ceiling.
- Filed
- Feb 10, 2025
- Issued
- Apr 29, 2025 (3 months after filing)
- Completed
- Oct 30, 2025 (6 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 19 stops across 4 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 6, 2025 | Feb 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 24, 2025 | Feb 24, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 24, 2025 | Mar 17, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2025 | Mar 28, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 24, 2025 | Mar 4, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 24, 2025 | Mar 18, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2025 | Mar 4, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 24, 2025 | Apr 23, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 16, 2025 | Apr 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 16, 2025 | Apr 16, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 16, 2025 | Apr 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 16, 2025 | Apr 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2025 | Apr 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 21, 2025 | Apr 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 21, 2025 | Apr 21, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 21, 2025 | Apr 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 21, 2025 | Apr 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 22, 2025 | Apr 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 23, 2025 | Apr 29, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $160,000
| Name | Role | License on permit |
|---|---|---|
| Mohammad Sharif Rahimian Atelier 424 | Architect | C-25912 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026