2090 23rd Av
San Francisco permit 202502100008 · Sunset/Parkside
1st/f: new family rm, new bedroom, new bath & hallway. 2nd/f: remodel e) bathrooms to 1 ensuite bath & 1 common bath. fill in e) non shared lightwell, & 2 new skylights. add new interier stair to connect both levels
- Filed
- Feb 10, 2025
- Issued
- Mar 11, 2025 (within 1 month of filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 10 stops across 4 departments
- Comments issued
- Once, by Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 10, 2025 | Feb 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 10, 2025 | Feb 10, 2025 | Approved |
Intake Building Inspection · INTAKE | Feb 21, 2025 | Feb 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 21, 2025 | Feb 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 21, 2025 | Feb 21, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 21, 2025 | Feb 21, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 21, 2025 | Feb 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 21, 2025 | Feb 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 21, 2025 | Feb 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2025 | Mar 11, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $221,000
| Name | Role | License on permit |
|---|---|---|
| Carlos Renan Dominguez | Architect | C26949 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025