1800 Owens St
San Francisco permit 202502100016 · Potrero Hill
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa # 202406255203: revisions include removal of sector 4 from scope & other revisions to sectors 2 & 3.
- Filed
- Feb 25, 2025
- Issued
- Aug 29, 2025 (6 months after filing)
- Completed
- Not completed yet
- Review stops
- 24 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 7, 2025 | Feb 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 24, 2025 | Feb 25, 2025 | Administrative |
Redevelopment review Redevelopment · REDEV | Feb 25, 2025 | Mar 13, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 25, 2025 | Apr 2, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 25, 2025 | Apr 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 25, 2025 | Apr 12, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 25, 2025 | Mar 7, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 25, 2025 | Mar 20, 2025 | Approved |
Public health review Public Health · HEALTH | Feb 25, 2025 | Feb 27, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Feb 25, 2025 | Aug 18, 2025 | Administrative |
Public Health HEALTH-HM | Feb 27, 2025 | Feb 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 29, 2025 | May 16, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2025 | May 5, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 29, 2025 | May 7, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 9, 2025 | Jul 18, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2025 | Aug 5, 2025 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2025 | Aug 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 5, 2025 | Aug 12, 2025 | Approved |
Redevelopment review Redevelopment · REDEV | Aug 6, 2025 | Aug 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 6, 2025 | Aug 6, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 7, 2025 | Aug 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 7, 2025 | Aug 8, 2025 | Approved |
Public Health HEALTH-HM | Aug 7, 2025 | Aug 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 18, 2025 | Aug 29, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Randall Robert Dowler Dga Planning Architecture | Architect | C23107 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026