1435 Stockton St
San Francisco permit 202502100048 · Chinatown
Tenant improvement to (e) us bank to include millwork, finishes, bank equipment & partitions /interior doors
- Filed
- Feb 10, 2025
- Issued
- Jun 24, 2025 (4 months after filing)
- Completed
- Sep 5, 2025 (2 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 11 stops across 2 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 10, 2025 | Feb 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 10, 2025 | Feb 10, 2025 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | Feb 11, 2025 | Feb 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2025 | Feb 11, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 11, 2025 | Feb 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 26, 2025 | Feb 26, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 10, 2025 | Mar 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 10, 2025 | Mar 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 10, 2025 | Mar 10, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 10, 2025 | Mar 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 24, 2025 | Jun 24, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $83,000
| Name | Role | License on permit |
|---|---|---|
| Scott Merrill Klopfer | Architect | C38207 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026