1439 Egbert Av
San Francisco permit 202502130311 · Bayview Hunters Point
Unit c -convert light manufacturing to pet kennel, no expansion or exterior change. (e) mechanical, plumbing no change and add area exhaust fan.
- Filed
- Feb 13, 2025
- Issued
- Apr 30, 2025 (2 months after filing)
- Completed
- Aug 20, 2025 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 6 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Feb 13, 2025 | Feb 13, 2025 | — |
Plumbing inspector Building Inspection · PID-INSP | Feb 13, 2025 | Feb 13, 2025 | — |
Intake Building Inspection · INTAKE | Feb 13, 2025 | Feb 13, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 13, 2025 | Feb 13, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Feb 20, 2025 | Feb 20, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 20, 2025 | Feb 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 20, 2025 | Feb 20, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 20, 2025 | Feb 20, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 13, 2025 | Mar 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 13, 2025 | Mar 13, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Mar 20, 2025 | Mar 20, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 20, 2025 | Mar 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 20, 2025 | Mar 20, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2025 | Mar 20, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Mar 27, 2025 | Mar 27, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Mar 27, 2025 | Mar 27, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 27, 2025 | Mar 27, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 27, 2025 | Mar 27, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2025 | Mar 27, 2025 | Approved |
Public health review Public Health · HEALTH | Mar 27, 2025 | Mar 27, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Mar 27, 2025 | Mar 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 27, 2025 | Mar 27, 2025 | Not Applicable |
Intake Building Inspection · INTAKE | Apr 22, 2025 | Apr 22, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 22, 2025 | Apr 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 30, 2025 | Apr 30, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Lei Zheng | Architect | C69809 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2018