5836 Geary Bl
San Francisco permit 202502140364 · Outer Richmond
Convert (e) 2/f offices to (2) residential units. enlarge one window in lightwell for egress. convert (e) ground floor roof to 2/f deck. no exterior expansion.
- Filed
- Jul 21, 2025
- Issued
- Oct 6, 2025 (3 months after filing)
- Completed
- Jun 5, 2026 (8 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 24 stops across 6 departments
- Comments issued
- 4 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 12, 2025 | Feb 27, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 20, 2025 | Apr 3, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 8, 2025 | Jul 15, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 21, 2025 | Jul 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 21, 2025 | Jul 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 21, 2025 | Aug 12, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 21, 2025 | Aug 7, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2025 | Jul 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 21, 2025 | Aug 1, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 21, 2025 | Jul 24, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 21, 2025 | Aug 28, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2025 | Jul 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 21, 2025 | Sep 17, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Jul 29, 2025 | Jul 29, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Aug 19, 2025 | Aug 19, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 2, 2025 | Sep 3, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 3, 2025 | Sep 4, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 3, 2025 | Sep 9, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 3, 2025 | Sep 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 3, 2025 | Sep 4, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 3, 2025 | Sep 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 3, 2025 | Sep 5, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Sep 17, 2025 | Sep 17, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2025 | Oct 6, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $288,368
| Name | Role | License on permit |
|---|---|---|
| My My Ly Mml Architect | Architect | C32972 |
| Erasmo De Luna Econ Build Inc | Engineer | C-91021 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023