CheckMyDesigner

5836 Geary Bl

San Francisco permit 202502140364 · Outer Richmond

Commercial or tenant improvementFull plan reviewComplete
Street view · Jan 2023
Google Street View of 5836 Geary Bl, Jan 2023
Scope of work
As written on the permit application.

Convert (e) 2/f offices to (2) residential units. enlarge one window in lightwell for egress. convert (e) ground floor roof to 2/f deck. no exterior expansion.

Timeline
Key dates from the city record.
Filed
Jul 21, 2025
Issued
Oct 6, 2025 (3 months after filing)
Completed
Jun 5, 2026 (8 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 6 departments
Comments issued
4 times, by Permit Center, Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 27, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Apr 3, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Jul 15, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 21, 2025Administrative

Zoning review

Planning · CP-ZOC

Jul 22, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 12, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 7, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jul 29, 2025Approved

Fire prevention review

Fire Department · SFFD

Aug 1, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jul 24, 2025Approved

Urban forestry

Public Works · DPW-BUF

Aug 28, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 24, 2025Approved

Permit Processing Center

Building Inspection · PPC

Sep 17, 2025Administrative

Mechanical plan review quality control

Building Inspection · MECH-QC

Jul 29, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Aug 19, 2025Administrative

Building plan review

Building Inspection · BLDG

Sep 3, 2025Approved

Zoning review

Planning · CP-ZOC

Sep 4, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 9, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 3, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Sep 4, 2025Approved

Urban forestry

Public Works · DPW-BUF

Sep 16, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 5, 2025Approved

Development fee collection

Building Inspection · DFCU

Sep 17, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Oct 6, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$288,368
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
My My Ly

Mml Architect

ArchitectC32972
Erasmo De Luna

Econ Build Inc

EngineerC-91021
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202502140364 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record