249 Mississippi St
San Francisco permit 202502140421 · Potrero Hill
Demolish a two-story, type 5, single family building.
- Filed
- May 19, 2025
- Issued
- Jan 27, 2026 (8 months after filing)
- Completed
- Not completed yet
- Review stops
- 16 stops across 5 departments
- Comments issued
- Twice, by Permit Center, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 10, 2025 | Feb 21, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 2, 2025 | May 16, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 19, 2025 | May 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 21, 2025 | Jul 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 21, 2025 | Jun 14, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 21, 2025 | Jun 15, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 21, 2025 | May 27, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 21, 2025 | May 27, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 21, 2025 | Sep 22, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 11, 2025 | Aug 12, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Aug 20, 2025 | Sep 15, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 20, 2025 | Aug 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 20, 2025 | Aug 25, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2025 | Aug 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2025 | Sep 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 22, 2025 | Jan 27, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Demolitions
- Status
- Issued
- Estimated cost
- $12,150
| Name | Role | License on permit |
|---|---|---|
| Craig E Steely Craig Steely Architecture | Architect | C26737 |
| Vladimir Rabichev Optimal Design Group | Engineer | C35314 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026