249 Mississippi St

San Francisco permit 202502140427 · Potrero Hill

New buildingFull plan reviewIssued
Street view · Sep 2026
Google Street View of 249 Mississippi St, Sep 2026
Scope of work
As written on the permit application.

Erect a four-story, type 5, residential building with two units.

Timeline
Key dates from the city record.
Filed
May 21, 2025
Issued
Jan 27, 2026 (8 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 6 departments
Comments issued
8 times, by Permit Center, Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 21, 2025Issued Comments

Permit Center

Permit Center · PERMIT-CTR

May 16, 2025Approved

Central Permit Bureau

Building Inspection · CPB

May 21, 2025Administrative

Zoning review

Planning · CP-ZOC

Jun 17, 2025Approved

Building plan review

Building Inspection · BLDG

Jun 15, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 15, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jul 15, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

May 27, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 27, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Jul 15, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 30, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Jun 2, 2025Approved-Stipulated

Permit Processing Center

Building Inspection · PPC

Sep 22, 2025Administrative

Building plan review

Building Inspection · BLDG

Jun 15, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Jul 15, 2025Approved

Fire prevention review

Fire Department · SFFD

Jul 23, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jul 29, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 28, 2025Approved

Fire prevention review

Fire Department · SFFD

Aug 12, 2025Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Aug 14, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Aug 13, 2025Approved-Stipulated

Zoning review

Planning · CP-ZOC

Sep 15, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 20, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 29, 2025Approved

Fire prevention review

Fire Department · SFFD

Aug 25, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Aug 27, 2025Approved

Urban forestry

Public Works · DPW-BUF

Sep 16, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 29, 2025Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Aug 21, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Sep 22, 2025Approved

Development fee collection

Building Inspection · DFCU

Sep 16, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Jan 27, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Issued
Estimated cost
$1,361,747
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Craig E Steely

Craig Steely Architecture

ArchitectC26737
Vladimir Rabichev

Optimal Design Group

EngineerC35314
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202502140427 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record