1369 Quesada Av
San Francisco permit 202502200728 · Bayview Hunters Point
Conversion of sfd with 4 bed, 3 baths into a 3 bed, 2 bath, kitchenette & laundry room + state adu with 1 bed, 1 bath,laundry closet. add door to top of interior stairs for sep entries for primary unit & state adu.additional renovations to primary kitchen & bathroom. new 2 level deck and stairs
- Filed
- Mar 31, 2025
- Issued
- Oct 15, 2025 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 36 stops across 6 departments
- Comments issued
- 12 times, by Permit Center, Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 19, 2025 | Mar 3, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 12, 2025 | Mar 31, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2025 | Apr 1, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 2, 2025 | Apr 8, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 2, 2025 | Apr 14, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2025 | Apr 9, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 2, 2025 | Apr 3, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2025 | Apr 7, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 2, 2025 | Apr 18, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 2, 2025 | Sep 2, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Apr 21, 2025 | Apr 21, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 18, 2025 | Jun 24, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 18, 2025 | Jun 20, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 18, 2025 | Jul 1, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2025 | Jun 25, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 18, 2025 | Jun 18, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 18, 2025 | Jul 1, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 18, 2025 | Jun 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2025 | Jun 23, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 22, 2025 | Aug 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 22, 2025 | Aug 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 22, 2025 | Jul 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 22, 2025 | Jul 23, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 22, 2025 | Jul 23, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 22, 2025 | Aug 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 22, 2025 | Jul 24, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 31, 2025 | Jul 31, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 14, 2025 | Aug 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 14, 2025 | Aug 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 14, 2025 | Aug 18, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 14, 2025 | Aug 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 14, 2025 | Aug 18, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 14, 2025 | Aug 26, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2025 | Aug 15, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Sep 2, 2025 | Sep 2, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 2, 2025 | Oct 15, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| David L K Hayes Dh | Ad | Architect | C-37960 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025