135 04th St
San Francisco permit 202502210883 · Financial District/South Beach
Suite fc8-interior ti install tap room bar. replacing an (e) cafe no change of occupancy, no exterior alteration. new work includes minor interior demo of (e) finishes and construction of new interior finishes, new interior storefront new furnishings and equipment. mep deferred.
- Filed
- Feb 21, 2025
- Issued
- Apr 22, 2025 (2 months after filing)
- Completed
- Sep 25, 2025 (5 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 12 stops across 5 departments
- Comments issued
- Twice, by Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 21, 2025 | Feb 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 24, 2025 | Feb 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 24, 2025 | Feb 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2025 | Feb 24, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 24, 2025 | Feb 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2025 | Feb 24, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 28, 2025 | Feb 28, 2025 | Approved |
Public health review Public Health · HEALTH | Feb 28, 2025 | Feb 28, 2025 | Administrative |
Public health food review Public Health · HEALTH-FD | Feb 28, 2025 | Mar 12, 2025 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Apr 10, 2025 | Apr 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 10, 2025 | Apr 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2025 | Apr 22, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Max A Crome Crome Architecture | Architect | C25487 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026