28 Day St
San Francisco permit 202502240915 · Noe Valley
Alteration/addition of existing 3-story, 2-unit (2-units + 1-unauthorized dwelling unit) residential building, resulting in a 4-story, 3-units residential building of upgraded units.
- Filed
- Mar 6, 2025
- Issued
- Oct 17, 2025 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 46 stops across 6 departments
- Comments issued
- 14 times, by Building Inspection, Fire Department, Public Works, Public Utilities, Planning
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 20, 2025 | Mar 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 24, 2025 | Mar 7, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 7, 2025 | Mar 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 7, 2025 | Apr 18, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 7, 2025 | Mar 26, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2025 | Mar 10, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 7, 2025 | Apr 11, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 7, 2025 | Mar 11, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 7, 2025 | Oct 10, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 14, 2025 | Apr 14, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 20, 2025 | Jul 1, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 25, 2025 | Jun 25, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2025 | Sep 18, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2025 | Aug 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 12, 2025 | Aug 12, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 15, 2025 | Aug 15, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 2, 2025 | Sep 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 11, 2025 | Sep 23, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 15, 2025 | Sep 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 19, 2025 | Sep 19, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 29, 2025 | Oct 2, 2025 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Oct 3, 2025 | Oct 3, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 10, 2025 | Oct 17, 2025 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 30, 2025 | Nov 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 19, 2025 | Dec 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 15, 2025 | Dec 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 15, 2025 | Jan 14, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 15, 2025 | Jan 16, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2025 | Jan 2, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 15, 2025 | Dec 18, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2025 | Dec 16, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 15, 2025 | Jan 16, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2025 | Dec 17, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 15, 2025 | Mar 9, 2026 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Jan 2, 2026 | Jan 2, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2026 | Feb 19, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2026 | Feb 17, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 18, 2026 | Feb 18, 2026 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Feb 20, 2026 | Feb 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 20, 2026 | Feb 20, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 25, 2026 | Feb 25, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 4, 2026 | Mar 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 5, 2026 | Mar 5, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 9, 2026 | Mar 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 9, 2026 | Apr 6, 2026 | Administrative |
Development fee collection Building Inspection · DFCU | Mar 12, 2026 | Mar 12, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $4,750,000
| Name | Role | License on permit |
|---|---|---|
| Neal J Z Schwartz Schwartz & Architecture | Architect | C-27065 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024