175 21st Av
San Francisco permit 202502240980 · Outer Richmond
Sb721 structural repairs, water proofing structural repairs, stucco replacement. to comply with nov #202430828 #2. repair decks unit 301,101,103,104,105,201
- Filed
- Feb 24, 2025
- Issued
- Mar 27, 2025 (1 month after filing)
- Completed
- Apr 13, 2026 (13 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 12 stops across 3 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Feb 24, 2025 | Feb 24, 2025 | Approved |
Intake Building Inspection · INTAKE | Feb 24, 2025 | Feb 24, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 24, 2025 | Feb 24, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 25, 2025 | Feb 25, 2025 | Issued Comments |
Apartment and hotel inspection Building Inspection · HIS | Feb 28, 2025 | Feb 28, 2025 | Approved |
Intake Building Inspection · INTAKE | Feb 28, 2025 | Feb 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 28, 2025 | Feb 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 27, 2025 | Mar 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 27, 2025 | Mar 27, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 27, 2025 | Mar 27, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 27, 2025 | Mar 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2025 | Mar 27, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| Christopher Benno Kahanek | Engineer | S5591 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025