120 Maiden Ln
San Francisco permit 202502251037 · Financial District/South Beach
(n) soffit above main entrance service door and side window replacement of (e) first floor glazing with (n) security glazing. (n) secuirty shutter at all first floor glazing. construction of 1 (n) face sign above entrance and one (n) blade sign above service door
- Filed
- Feb 25, 2025
- Issued
- Jul 18, 2025 (5 months after filing)
- Completed
- Feb 5, 2026 (7 months after issuance)
- Review stops
- 17 stops across 5 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 25, 2025 | Feb 25, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Feb 25, 2025 | Feb 25, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 8, 2025 | Apr 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 9, 2025 | Apr 9, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | May 9, 2025 | May 9, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 9, 2025 | May 9, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 9, 2025 | May 9, 2025 | Approved |
Intake Building Inspection · INTAKE | May 16, 2025 | May 16, 2025 | Administrative |
Building plan review Building Inspection · BLDG | May 21, 2025 | May 21, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 21, 2025 | May 21, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | May 21, 2025 | May 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 21, 2025 | May 21, 2025 | Not Applicable |
Intake Building Inspection · INTAKE | May 28, 2025 | May 28, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | May 28, 2025 | May 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 29, 2025 | May 29, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 30, 2025 | May 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 18, 2025 | Jul 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| James Louis Zak Wz Architecture | Architect | C21506 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025