150 Eureka St
San Francisco permit 202502271195 · Castro/Upper Market
Legalize 3 storage units into local adu's. no construction work.
- Filed
- Mar 19, 2025
- Issued
- Jun 13, 2025 (3 months after filing)
- Completed
- Jun 18, 2025 (within 1 month of issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 18 stops across 6 departments
- Comments issued
- 5 times, by Planning, Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 25, 2025 | Mar 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 20, 2025 | Mar 20, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 20, 2025 | Mar 27, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 20, 2025 | Apr 3, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2025 | Apr 1, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 20, 2025 | Mar 25, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 20, 2025 | Mar 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 20, 2025 | Mar 25, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 20, 2025 | May 20, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Apr 28, 2025 | Apr 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 30, 2025 | Apr 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 30, 2025 | Apr 30, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 2, 2025 | May 2, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 5, 2025 | May 7, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2025 | May 7, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2025 | May 20, 2025 | Approved |
Development fee collection Building Inspection · DFCU | May 20, 2025 | May 20, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 20, 2025 | Jun 13, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $455,556
| Name | Role | License on permit |
|---|---|---|
| Gary Stephenson Gee Gary Gee Architects, Inc. | Architect | C14060 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2018