2100 Webster St
San Francisco permit 202502271212 · Pacific Heights
3/fl-suite 331-332- ti for medical offices to include non structrual partitions, finishes, fixtures, equipment and mep
- Filed
- Feb 27, 2025
- Issued
- May 2, 2025 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 11 stops across 5 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 27, 2025 | Feb 27, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 27, 2025 | Feb 27, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2025 | Feb 27, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 27, 2025 | Feb 27, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 27, 2025 | Feb 27, 2025 | Not Applicable |
Electrical plan review Building Inspection · MECH-E | Mar 7, 2025 | Mar 7, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 10, 2025 | Mar 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 10, 2025 | Mar 10, 2025 | Approved |
Public health review Public Health · HEALTH | Mar 10, 2025 | Mar 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 2, 2025 | May 2, 2025 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | May 2, 2025 | May 2, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $590,780
| Name | Role | License on permit |
|---|---|---|
| Ross Allen Hummel Lineoffice Arch. | Architect | C31282 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025