1908 Broadway
San Francisco permit 202502281303 · Pacific Heights
Entry level - remove wall between kitchen and dining. remodel kitchen. move powder room. reconfigure lower stairs. upper level - remodel master bath and bedroom. add 1 new bedroom. no exterior work. no new sq.ft.
- Filed
- Feb 28, 2025
- Issued
- Mar 13, 2025 (within 1 month of filing)
- Completed
- Dec 17, 2025 (9 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 5 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 28, 2025 | Feb 28, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 28, 2025 | Feb 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 28, 2025 | Feb 28, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 28, 2025 | Feb 28, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2025 | Mar 13, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $210,000
| Name | Role | License on permit |
|---|---|---|
| Steven Carl Geiszler Geiszler Architects | Architect | C24557 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025