1140 Ingerson Av
San Francisco permit 202503031415 · Bayview Hunters Point
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to ref 202212309561 & 9562. occup reversal to maintain as r3. wall btwn garage and corr. w/o fdn. detail 3/s1 not apply. shear wall on grid d and 6'-2" and d+3 is 4' tall use hdu4 instead of hud8. new deck is 10" higher than 1st flr elevation. no fire sprinklers.
- Filed
- Mar 31, 2025
- Issued
- Dec 11, 2025 (8 months after filing)
- Completed
- Oct 22, 2026 (10 months after issuance)
- Review stops
- 19 stops across 4 departments
- Comments issued
- 7 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 25, 2025 | Mar 10, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 17, 2025 | Mar 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 31, 2025 | Mar 31, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 31, 2025 | Apr 21, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 31, 2025 | Apr 1, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 31, 2025 | Dec 9, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 14, 2025 | Apr 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 23, 2025 | May 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 13, 2025 | May 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 19, 2025 | May 19, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 12, 2025 | Jun 12, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 12, 2025 | Jun 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 13, 2025 | Aug 25, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 10, 2025 | Dec 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 10, 2025 | Nov 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 10, 2025 | Nov 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 10, 2025 | Nov 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 12, 2025 | Nov 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 9, 2025 | Dec 11, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Seri Ngernwattana Seri Ngerwattana, Pe | Engineer | C66949 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026