2350 Turk Bl
San Francisco permit 202503041492 · Lone Mountain/USF
Renovation of (e) theater includng installation of new cat- walk over (e) stage
- Filed
- Apr 11, 2025
- Issued
- Oct 6, 2025 (6 months after filing)
- Completed
- Jul 28, 2026 (10 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 24 stops across 4 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 4, 2025 | Mar 4, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 4, 2025 | Mar 4, 2025 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Mar 18, 2025 | Apr 1, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 4, 2025 | Apr 11, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 11, 2025 | May 29, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 11, 2025 | May 28, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 11, 2025 | May 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 11, 2025 | May 13, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 11, 2025 | Sep 23, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 25, 2025 | Jul 2, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 25, 2025 | Jul 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2025 | Jul 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 25, 2025 | Jun 25, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 14, 2025 | Jul 16, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 14, 2025 | Jul 23, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 14, 2025 | Aug 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 25, 2025 | Jul 29, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 25, 2025 | Jul 29, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2025 | Aug 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 4, 2025 | Sep 8, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 4, 2025 | Sep 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 4, 2025 | Sep 19, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 4, 2025 | Sep 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2025 | Oct 6, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $990,000
| Name | Role | License on permit |
|---|---|---|
| Robert S Connelly Oculus | Architect | C27077 |
| Matthew Palmer Frantz Zfa Strutural Engineers | Engineer | S5919 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023