San Francisco permit 202503041492 · Lone Mountain/USF

Commercial or tenant improvementFull plan reviewComplete
Street view · Jan 2023
Google Street View of 2350 Turk Bl, Jan 2023
Scope of work
As written on the permit application.

Renovation of (e) theater includng installation of new cat- walk over (e) stage

Timeline
Key dates from the city record.
Filed
Apr 11, 2025
Issued
Oct 6, 2025 (6 months after filing)
Completed
Jul 28, 2026 (10 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 4 departments
Comments issued
8 times, by Building Inspection, Fire Department
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Mar 4, 2025Administrative

Zoning review

Planning · CP-ZOC

Mar 4, 2025Not Applicable

Permit Center

Permit Center · PERMIT-CTR

Apr 1, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Apr 11, 2025Administrative

Building plan review

Building Inspection · BLDG

May 29, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

May 28, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 17, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

May 13, 2025Issued Comments

Permit Processing Center

Building Inspection · PPC

Sep 23, 2025Administrative

Building plan review

Building Inspection · BLDG

Jul 2, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 11, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 16, 2025Approved

Fire prevention review

Fire Department · SFFD

Jun 25, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jul 16, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 23, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 1, 2025Approved

Building plan review

Building Inspection · BLDG

Jul 29, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Jul 29, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 1, 2025Approved

Building plan review

Building Inspection · BLDG

Sep 8, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 23, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 19, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 12, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 6, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$990,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Robert S Connelly

Oculus

ArchitectC27077
Matthew Palmer Frantz

Zfa Strutural Engineers

EngineerS5919
Sources