286 San Jose Av #0
San Francisco permit 202503061664 · Mission
Dry rot repair around the garage door. repair sticco as needed. garage openign stays the same. replace header and install new columns
- Filed
- Mar 6, 2025
- Issued
- Mar 24, 2025 (within 1 month of filing)
- Completed
- Apr 9, 2025 (within 1 month of issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 7 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 6, 2025 | Mar 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 6, 2025 | Mar 6, 2025 | Approved |
Intake Building Inspection · INTAKE | Mar 24, 2025 | Mar 24, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 24, 2025 | Mar 24, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 24, 2025 | Mar 24, 2025 | Not Applicable |
Building plan review Building Inspection · BLDG | Mar 24, 2025 | Mar 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 24, 2025 | Mar 24, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $19,512
| Name | Role | License on permit |
|---|---|---|
| Daniel Chen | Engineer | C77440 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026