2448 Folsom St
San Francisco permit 202503061731 · Mission
2/f interior remodel to relocate main bath and add new hall bath. open 144 sq ft of unfinished attic to hall below, provide new insulation. (2) new skylights. mechanical, electrical, and plumbing rerouting and upgrading in area of work. replace 4 windows 1 facing st. u>.30
- Filed
- Mar 6, 2025
- Issued
- May 12, 2025 (2 months after filing)
- Completed
- Mar 3, 2026 (10 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 14 stops across 3 departments
- Comments issued
- 3 times, by Building Inspection, Public Utilities, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 6, 2025 | Mar 6, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 6, 2025 | Mar 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 6, 2025 | Mar 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 13, 2025 | Mar 13, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 13, 2025 | Mar 13, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 13, 2025 | Mar 13, 2025 | Approved |
Intake Building Inspection · INTAKE | Apr 24, 2025 | Apr 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 24, 2025 | Apr 24, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 28, 2025 | Apr 28, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 28, 2025 | Apr 28, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 28, 2025 | Apr 28, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 1, 2025 | May 1, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2025 | May 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 12, 2025 | May 12, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| Dennis C Budd Dennis Budd Aia Architect | Architect | C26969 |
| Reece Relatores Relatores Structural | Engineer | C84126 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023