1211 A Revere Av
San Francisco permit 202503061742 · Bayview Hunters Point
1/f: legalize space into accessory dwelling unit.
- Filed
- Mar 20, 2025
- Issued
- Oct 8, 2025 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 20 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 4, 2025 | Mar 19, 2025 | Approved |
Apartment and hotel inspection Building Inspection · HIS | Mar 19, 2025 | Mar 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 21, 2025 | Mar 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 21, 2025 | Apr 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 21, 2025 | Apr 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 21, 2025 | Apr 3, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 21, 2025 | Mar 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 21, 2025 | Mar 24, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 21, 2025 | Mar 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 21, 2025 | Mar 24, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 21, 2025 | May 21, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2025 | Mar 25, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 6, 2025 | May 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2025 | May 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 6, 2025 | May 20, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 6, 2025 | May 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 6, 2025 | May 7, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 6, 2025 | May 20, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2025 | May 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 21, 2025 | Oct 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $130,912
| Name | Role | License on permit |
|---|---|---|
| Stacy Chien-Yu Lin | Architect | C30812 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025