16 West Clay St
San Francisco permit 202503101927 · Seacliff
Minor horizontal addition at 3rd level only. (180 sq ft). at front of home: new closet & exercise space. addition is setback from facade by 5'-3". remove non-historic balaustrades at front, side & rear facades reconstructing closer to original design. reconstruct clay tile rooflets over two front
- Filed
- Mar 14, 2025
- Issued
- Sep 16, 2025 (6 months after filing)
- Completed
- May 11, 2026 (8 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 23 stops across 6 departments
- Comments issued
- Once, by Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 28, 2025 | Mar 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2025 | Mar 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 17, 2025 | Mar 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 17, 2025 | Jun 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 17, 2025 | Apr 13, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 17, 2025 | Mar 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 17, 2025 | Mar 19, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 17, 2025 | Mar 18, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 17, 2025 | Sep 12, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Apr 1, 2025 | Apr 1, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 11, 2025 | Jun 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 11, 2025 | Jun 11, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 11, 2025 | Jul 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 11, 2025 | Jun 12, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jun 11, 2025 | Jun 20, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2025 | Jun 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 4, 2025 | Sep 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 4, 2025 | Sep 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 4, 2025 | Sep 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 4, 2025 | Sep 9, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2025 | Sep 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2025 | Sep 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 12, 2025 | Sep 16, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Thomas Rex Hardy Thomas Rex Hardy, Aia | Architect | C12683 |
| Diarmuid Hugo Mac Neill Dolmen Structural Engineer | Engineer | C56739 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025