255 Henry St
San Francisco permit 202503111975 · Castro/Upper Market
The project is an kind replacement of a 2 story wood framed exit stair and covered porches. includes: new exterior finishes, windows, and exterior doors at the south facade. new shear walls and foundation at the south facade and a voluntary siesmic strengthening within the garage.
- Filed
- Apr 10, 2025
- Issued
- Feb 27, 2026 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 13 stops across 3 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 7, 2025 | Mar 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 31, 2025 | Apr 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 10, 2025 | Jun 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2025 | May 13, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2025 | May 19, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 10, 2025 | Feb 6, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Nov 7, 2025 | Nov 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 7, 2025 | Nov 13, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2025 | Nov 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 21, 2026 | Jan 22, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Feb 6, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2026 | Jan 29, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2026 | Feb 27, 2026 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Vaughn A Johnson | Payor | C-33836 |
| Daniel Antonio Bastiao Daniel A Bastiao Design | Engineer | C71442 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025