150 Oak St
San Francisco permit 202503132189 · Hayes Valley
Ab-004 priority: phase 1a:partial interior non-structural t.i. work on the 4/f & basement. provide make-up air using the (e) mehanical system by rerouting ductwork and air diffusers where applicable. no increase to student population.
- Filed
- Mar 13, 2025
- Issued
- May 14, 2025 (2 months after filing)
- Completed
- May 5, 2026 (12 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 15 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 12, 2025 | Mar 24, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 24, 2025 | Mar 24, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 24, 2025 | Apr 8, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 24, 2025 | Apr 8, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 24, 2025 | Mar 31, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 24, 2025 | May 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 24, 2025 | Mar 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2025 | Mar 27, 2025 | Not Applicable |
Public health review Public Health · HEALTH | Mar 24, 2025 | Mar 26, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Mar 24, 2025 | May 12, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 18, 2025 | Apr 21, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 21, 2025 | Apr 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 8, 2025 | May 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 9, 2025 | May 12, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 12, 2025 | May 14, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Joshua Sawyer Cohn Ca Architects | Architect | C23410 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025