150 Oak St
San Francisco permit 202503172389 · Hayes Valley
Ab-004 priority:phase 1b: renovate restrooms on floors 1-5.replace (e) toilet partitions w/ proviacy partitions where allwed by (e) fixture layouts.additoinal gender neutral restroom added to basement & 6/f.expand (e) egress stairs #05 from 1-2/f to service basements thru 3/f.add stairs #8 fr 3-6/f.
- Filed
- Mar 17, 2025
- Issued
- Jun 10, 2025 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 14, 2025 | Mar 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 28, 2025 | Mar 28, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 28, 2025 | Apr 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 28, 2025 | Apr 11, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 28, 2025 | Apr 8, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 28, 2025 | Apr 10, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 28, 2025 | Apr 1, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 28, 2025 | Apr 4, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 28, 2025 | Apr 1, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 28, 2025 | Jun 4, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Apr 11, 2025 | Apr 11, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 21, 2025 | Jun 3, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 21, 2025 | May 30, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 21, 2025 | May 21, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 21, 2025 | May 30, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 21, 2025 | May 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2025 | May 28, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 3, 2025 | Jun 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 4, 2025 | Jun 10, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Joshua Sawyer Cohn Ca Architects | Architect | C23410 |
| Chris Warner Zfa Structural Engineers | Engineer | S4613 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025