130 Madrone Av
San Francisco permit 202503182445 · West of Twin Peaks
Window and siding replacement in kind. interior remodel. modify existing exterior rear deck. no building envelope expansion
- Filed
- Apr 10, 2025
- Issued
- Jul 30, 2025 (4 months after filing)
- Completed
- Mar 5, 2026 (7 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 21 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 18, 2025 | Mar 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 18, 2025 | Mar 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 19, 2025 | Mar 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2025 | Mar 19, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 20, 2025 | Apr 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2025 | Apr 15, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 15, 2025 | Jun 3, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 15, 2025 | Jun 3, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2025 | Apr 25, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 15, 2025 | Jul 25, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 3, 2025 | Jun 3, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Jun 3, 2025 | Jun 3, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 23, 2025 | Jun 23, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 24, 2025 | Jun 27, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 11, 2025 | Jul 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 15, 2025 | Jul 23, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2025 | Jul 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2025 | Jul 18, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2025 | Jul 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 23, 2025 | Jul 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 25, 2025 | Jul 30, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $650,000
| Name | Role | License on permit |
|---|---|---|
| David Swetz Swetzshop | Architect | C37457 |
| Reece Relatores Relatores Structural | Engineer | C84126 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023