San Francisco permit 202503212726 · Oceanview/Merced/Ingleside
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa 2023-0117-0234 replace garage concrete slab post footings and beams. new retaining walls in the backyard, building extends 16" in the back, new permeable pavers in the back. 14" of added new foundation
- Filed
- May 22, 2025
- Issued
- Mar 23, 2026 (10 months after filing)
- Completed
- Not completed yet
- Review stops
- 46 stops across 5 departments
- Comments issued
- 10 times, by Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 21, 2025 | Mar 21, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 21, 2025 | Mar 21, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Apr 14, 2025 | Apr 14, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 14, 2025 | Apr 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 5, 2025 | May 27, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | May 7, 2025 | May 20, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 27, 2025 | Jun 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 27, 2025 | Jul 16, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 27, 2025 | Jul 8, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 27, 2025 | May 28, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 27, 2025 | May 29, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 27, 2025 | Mar 12, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jun 26, 2025 | Jul 1, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 26, 2025 | Jun 27, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 26, 2025 | Jun 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 8, 2025 | Sep 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2025 | Sep 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2025 | Sep 22, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 8, 2025 | Sep 10, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2025 | Sep 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 16, 2025 | Oct 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2025 | Oct 23, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2025 | Oct 24, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 16, 2025 | Oct 20, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2025 | Oct 21, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 21, 2025 | Dec 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2025 | Nov 26, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2025 | Dec 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 21, 2025 | Nov 24, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2025 | Nov 26, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 21, 2026 | Jan 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Jan 30, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2026 | Jan 30, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 21, 2026 | Jan 26, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2026 | Jan 22, 2026 | Approved |
Zoning review Planning · CP-ZOC | Feb 2, 2026 | Feb 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 2, 2026 | Feb 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 2, 2026 | Feb 11, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 2, 2026 | Feb 3, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2026 | Feb 6, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 3, 2026 | Mar 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 3, 2026 | Mar 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2026 | Mar 11, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 3, 2026 | Mar 5, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2026 | Mar 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 12, 2026 | Mar 23, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $40,310
| Name | Role | License on permit |
|---|---|---|
| Daniel Chen Innodez | Engineer | C77440 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2014