1454 Cortland Av
San Francisco permit 202503212816 · Bernal Heights
Vertical addition for a new master suite with a bathroom, a bedroom, and walk-in closet. an attic access door will be provided.adu issued sep pa202301109994. toter storage, reconfi entry stair, hand/guardrail, deck over garage, new retaining wall, light and
- Filed
- Aug 4, 2025
- Issued
- Mar 24, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 8 times, by Permit Center, Planning, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 18, 2025 | Mar 28, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 28, 2025 | May 12, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 22, 2025 | Jun 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2025 | Aug 13, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 13, 2025 | Aug 14, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 13, 2025 | Sep 11, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 13, 2025 | Sep 16, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 13, 2025 | Sep 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 13, 2025 | Aug 21, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 13, 2025 | Aug 15, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 13, 2025 | Jan 15, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Nov 5, 2025 | Nov 5, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2025 | Nov 13, 2025 | Approved |
Zoning review Planning · CP-ZOC | Nov 17, 2025 | Nov 17, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 24, 2025 | Nov 25, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 8, 2026 | Jan 14, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 9, 2026 | Jan 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2026 | Jan 14, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 9, 2026 | Jan 14, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 14, 2026 | Jan 14, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jan 15, 2026 | Jan 15, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 15, 2026 | Mar 24, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $332,698
| Name | Role | License on permit |
|---|---|---|
| Steven Paul Duquette Duquette Engineering | Engineer | S3019 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025