San Francisco permit 202503253024 · Mission

Commercial or tenant improvementFull plan reviewIssued
Street view · Feb 2025
Google Street View of 1815 Market St, Feb 2025
Scope of work
As written on the permit application.

Building enlargement -to add level 2, remodel restaurant and change of occupancy

Timeline
Key dates from the city record.
Filed
Apr 10, 2025
Issued
Oct 22, 2025 (6 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
50 stops across 7 departments
Comments issued
15 times, by Building Inspection, Fire Department, Public Utilities, Public Health
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 9, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Apr 10, 2025Administrative

Zoning review

Planning · CP-ZOC

May 28, 2025Approved

Building plan review

Building Inspection · BLDG

May 22, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

May 28, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

May 28, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

May 6, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 2, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 24, 2025Issued Comments

Public health review

Public Health · HEALTH

Apr 11, 2025Administrative

Permit Processing Center

Building Inspection · PPC

Oct 6, 2025Administrative

Public health food review

Public Health · HEALTH-FD

Apr 25, 2025Issued Comments

Electrical plan review

Building Inspection · MECH-E

Apr 29, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 23, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 2, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Jun 24, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Jun 24, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jun 27, 2025Administrative

Building plan review

Building Inspection · BLDG

Jul 16, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 27, 2025Approved

Fire prevention review

Fire Department · SFFD

Jul 9, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 14, 2025Approved

Public health food review

Public Health · HEALTH-FD

Jul 10, 2025Approved

Zoning review

Planning · CP-ZOC

Jul 31, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 6, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 4, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 5, 2025Issued Comments

Public health food review

Public Health · HEALTH-FD

Jul 30, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Jul 29, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Jul 31, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 27, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 26, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Aug 20, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Aug 20, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 26, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Aug 27, 2025Approved

Public health food review

Public Health · HEALTH-FD

Aug 20, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Aug 21, 2025Approved

Building plan review

Building Inspection · BLDG

Sep 16, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 18, 2025Approved

Public health food review

Public Health · HEALTH-FD

Sep 17, 2025Approved

Zoning review

Planning · CP-ZOC

Sep 23, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 23, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 22, 2025Approved

Electrical plan review

Building Inspection · MECH-E

Sep 22, 2025Approved

Fire prevention review

Fire Department · SFFD

Sep 19, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Sep 24, 2025Approved

Development fee collection

Building Inspection · DFCU

Sep 24, 2025Administrative

Electrical plan review

Building Inspection · MECH-E

Sep 25, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Oct 22, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,400,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jason B Jones

Arcsine

Architect28018
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202503253024 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record