1073 Filbert St
San Francisco permit 202503263093 · Russian Hill
Interior remodel of upper unit to include infill of (e) light well, remodeled kitchen, dining room, guest bathroom, primary suite and den. new interior finishes, partitions, doors, ceilings, lighting and plumbing fixtures throughout upper unit. exterior work: window replacement at 2nd & 3rd fl.
- Filed
- May 23, 2025
- Issued
- Oct 22, 2025 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 35 stops across 5 departments
- Comments issued
- 13 times, by Planning, Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 26, 2025 | Mar 26, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 26, 2025 | Mar 26, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Apr 1, 2025 | Apr 1, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 1, 2025 | Apr 1, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Apr 11, 2025 | Apr 28, 2025 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Apr 16, 2025 | May 27, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | May 9, 2025 | May 21, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 27, 2025 | Sep 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 27, 2025 | Jul 25, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 27, 2025 | Jul 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 27, 2025 | Jul 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 27, 2025 | Jun 12, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 27, 2025 | Jun 4, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 27, 2025 | Oct 16, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Aug 8, 2025 | Aug 20, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 8, 2025 | Aug 13, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 8, 2025 | Aug 14, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 15, 2025 | Aug 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 19, 2025 | Aug 19, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 28, 2025 | Sep 11, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 28, 2025 | Sep 2, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 28, 2025 | Sep 4, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2025 | Sep 9, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Sep 10, 2025 | Sep 10, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 15, 2025 | Sep 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 22, 2025 | Sep 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 23, 2025 | Sep 23, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 1, 2025 | Oct 1, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 2, 2025 | Oct 6, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2025 | Oct 3, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 2, 2025 | Oct 7, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 2, 2025 | Oct 2, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2025 | Oct 3, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Oct 16, 2025 | Oct 16, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 16, 2025 | Oct 22, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| Brian T Milford Martinkovic Milford Architects | Architect | C33430 |
| Ashley M Wallace Martinkovic Milford Architects | Architect | C38112 |
| Shaun Edward Moynahan Semco Engineering | Engineer | S4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022