914 Capitol Av
San Francisco permit 202503273235 · Oceanview/Merced/Ingleside
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Altered site permit #201910013220. scope includes addition to the rear of the house including 1/f storage room. 2/f bedroom, full bath, & laundry. legalize of (e) structure built prior to current owner.
- Filed
- Apr 10, 2025
- Issued
- May 7, 2025 (within 1 month of filing)
- Completed
- Not completed yet
- Review stops
- 25 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 21, 2025 | Mar 31, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2025 | Apr 10, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 10, 2025 | Apr 22, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2025 | Apr 11, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2025 | Apr 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2025 | Apr 24, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 10, 2025 | May 1, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 1, 2025 | May 7, 2025 | Administrative |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 14, 2025 | May 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 28, 2025 | Jun 4, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 4, 2025 | Aug 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 4, 2025 | Jun 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 4, 2025 | Jun 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 4, 2025 | Jun 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 4, 2025 | Jun 6, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 4, 2025 | Jun 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 4, 2025 | Jun 10, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 4, 2025 | Aug 11, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jul 9, 2025 | Jul 9, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 9, 2025 | Jul 9, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 15, 2025 | Jul 16, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 16, 2025 | Jul 17, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 16, 2025 | Jul 22, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2025 | Jul 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 11, 2025 | Aug 19, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $1,000
| Name | Role | License on permit |
|---|---|---|
| Mark Douglas Brand Mark Brand Architecture | Architect | C13145 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2018