685 Market St
San Francisco permit 202503283304 · Financial District/South Beach
1st & 2nd fl - interconnecting stair between levels 1-2; (n) gender neutral rr on ground floor, new ground floor janitor's closet & door to courtyard.
- Filed
- Mar 28, 2025
- Issued
- Apr 21, 2025 (within 1 month of filing)
- Completed
- Jun 22, 2026 (14 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- Twice, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Mar 28, 2025 | Mar 28, 2025 | Administrative |
Intake Building Inspection · INTAKE | Mar 28, 2025 | Mar 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 31, 2025 | Mar 31, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 3, 2025 | Apr 3, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 3, 2025 | Apr 3, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 4, 2025 | Apr 4, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 4, 2025 | Apr 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 8, 2025 | Apr 8, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 8, 2025 | Apr 8, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 9, 2025 | Apr 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 21, 2025 | Apr 21, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $315,000
| Name | Role | License on permit |
|---|---|---|
| Victoria Lynn Salgado | Architect | C37053 |
| Barry Steven Wenger | Engineer | S7036 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022