65 Raycliff Tr
San Francisco permit 202503283337 · Pacific Heights
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision 202406174663- 1st floor kitchen, study , dining , entry remodel, 2nd floor master suite, reconfigure (e) stairs and guard rails to be up to code. remove (e) bathroom #3. 3rd floor multi purpose room remodel, and add (n) powder room and support for (e) deck cantilever. mep design build as
- Filed
- May 29, 2025
- Issued
- Jul 28, 2026 (14 months after filing)
- Completed
- Not completed yet
- Review stops
- 21 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 28, 2025 | Mar 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 28, 2025 | Mar 28, 2025 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | May 1, 2025 | May 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 27, 2025 | Jun 3, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 3, 2025 | Jun 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 3, 2025 | Jul 30, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 3, 2025 | Aug 14, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2025 | Jul 19, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 3, 2025 | Jun 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 3, 2025 | Jun 11, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 3, 2025 | Jul 20, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 17, 2026 | May 4, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Apr 29, 2026 | Apr 29, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 29, 2026 | Jun 4, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 5, 2026 | Jun 10, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 5, 2026 | Jun 15, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2026 | Jun 17, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2026 | Jun 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 5, 2026 | Jun 17, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 8, 2026 | Jul 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 20, 2026 | Jul 28, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Peter A Zepponi Zepponi Architects | Architect | C26699 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022